Thursday, October 28, 2010

Check out this video of our recent rail project....click an option below.

YouTube

The RIX Group completing "Stage 1" of a recent cold and rainy project. The project entailed over 100m² de-vegetation and scaling of loose material, the installation of 50 x 3m soil nails, the installation of 160m² of SL41 galvanised mesh and the placement of 25m³ of 25MPa Shotcrete. "Stage 1" was completed in 18hrs.

Sunday, October 24, 2010

Sharp and Straight Shotcrete Edges


Hi All,

The pool is now taking shape with the first spray successfully completed. Pictured is the pouring of the floor also visible is the sharp straight edges of a high class shotcrete finish.

Talk Soon

Team Nowra

Friday, October 8, 2010

Pool Ready for Steel Placement

Hi All,


With the top excavation completed and the lower pool drilled and bolted, a scaffold has been installed to assist the steel fixers in placing the steel reinforcement.


Talk Soon

Team Nowra

Sunday, October 3, 2010

Rail Corridor Stabilisation


Hi All,

RIX were busy this weekend with Railway corridor works. Scheduled rail network shutdowns enabled routine cutting stabilisation to proceed.

Talk soon...

Tuesday, September 21, 2010

Top Level - Shotcrete Complete

Well,
today was the day to cover roughly 20 x 4m horizontal drains, our 140 x 4.2m or so DCP bolts and our 3tonne of SL81 (approx.).
The spray was completed successfully and our nossle man Rod gave it a consistent uniform finish, no lumps or bumps.
James cut the tops gun barrel to the green line. Overall a fantastic gun finish result, the client is very happy with program and product.
Now we start on the pool! Talk soon...

Sunday, September 19, 2010

Top Level ready to Spray


Hi All,

Work was hampered but not stopped by the last deluge of rain which flooded the site and nearby highway. Steel is completed on the top level and bolting commences down in the pool excavation…

Talk soon
Team Nowra

Saturday, September 11, 2010

10/09/10 - S.Nowra - Steel Fixing Commences


Hi All,

Steel fixing commenced today SL81 galvanised mesh. Vertical strip drains are placed @ 1m centres, connecting to 4m drilled horizontal drains @ 3m centres. There is substantial water flowing from the excavation.
In the photo below Jimmy is setting the mesh while the Client's Surveyor is marking face of shotcrete.

Talk soon...

9/9/2010 - S.Nowra - Upper Level Drilling Nears Completion

Hi All,

Drilling has almost finished on the top level..
As a great man once said "That rock, is harder than a bulls forehead!!!". Our Drilling Manager has been trialing new drilling configurations with great success. Rotary or percussion, hydraulics or air. We have found with this rock rotary is slower but easier on the gear.
Hope to commence steel fixing later this week.

Talk soon ....


31/08/10 - S.Nowra- Shotcrete Pool

Hi All,


Established today.
This project is in a sensitive site.
We will be drilling and installing 4.2m rock bolts, 4m weep drains and shotcreting a large pool.

Talk Soon
Team Nowra

New Sydney HQ Update

The New Sydney Headquarters is moving along. Haven't been out there yet??

Watch the video below and catch up on the progress....



Regards
RIX Blogger