Steel fixing commenced today SL81 galvanised mesh. Vertical strip drains are placed @ 1m centres, connecting to 4m drilled horizontal drains @ 3m centres. There is substantial water flowing from the excavation.
In the photo below Jimmy is setting the mesh while the Client's Surveyor is marking face of shotcrete.