Thursday, October 28, 2010

Check out this video of our recent rail project....click an option below.

YouTube

The RIX Group completing "Stage 1" of a recent cold and rainy project. The project entailed over 100m² de-vegetation and scaling of loose material, the installation of 50 x 3m soil nails, the installation of 160m² of SL41 galvanised mesh and the placement of 25m³ of 25MPa Shotcrete. "Stage 1" was completed in 18hrs.